Friday, December 27, 2019

Solar Energy and Oncor

Okay, groovy people-
We got an email from Oncor on December 17 saying that we've been "moved to Project Submitted status." Unlike what we were initially told, the email says that the process may take up to 30 days to complete... not 2 weeks.  Strike one.  Hopefully the letter was erring on the side of caution and the 2 weeks will be closer to correct.  We'll see.  (Along with this, the email went straight to SPAM and was not listed as being from Oncor so I didn't see it for a week. Guess I'll have to scrutinize things more carefully.)

What that means is that we've got our system installed but can't switch it on. Not happy about this.  We'll survive, but not a fan of inaccurate information from companies. 

Also I have yet to hear from the company about scheduling the work on the "blackout circuits".  In their defense, it has been Christmas holidays, so I guess I can cut them a little slack, but we ARE rolling into blackout season shortly.  A well...again...we'll see.